HSBC NEW HEAD OFFICE BUILDING

COUNTRY
TURKEY
LOCATION
İSTANBUL
CLIENT
BOVIS
COMPLETION
2004
SERVICES
  • Grounding System

    • IT Equipments
    • System Room
    • Treasury Floor
    • IT Department

    For IT Rooms in Banking Department

    • Communication System
    • Static Grounding
    • Isolation System for IT System Room Using 4x250 kVA Isolation Transformer

     Lightning Protection System

    • Faraday Cage Protection System for Exterior Building
    • Surge Arrester Protection System for Interior Building
  • Test and commissioning starts when the project phase finishes, it is the last step before the project gets fully operational. In this step, systems in facility are being subjected to some functional and performance tests. As the result, system elements should be verified to work together without a problem and ready to go functional. This process is about testing the systems, reporting the outcomes and ensure everything operates how it’s supposed to operate. Client, manufacturers, contractors are all present on site during this process. Especially systems such as generators, uninterruptible power supplies, fire detection and alarm systems, lightings and etc. are the main focus points.

    Test and commissioning controls consists of two stages.

    1. Compliance Controls with the Project

    • Determination of presence of the products stated in the projects
    • Compatibility to specifications and brand list of the products used on site
       

    2. Site Controls

    • Visual inspections and connection controls (Level-3)
    • Function controls of the equipment (Level-4)
    • Function tests according the scenario (Level-5)
       

    After the test and commissioning is completed, process results are being reported. This report consists the signatures of the companies and people present at this process.

    Proen Engineering handles and manages test and commissioning phase with a great care, careful to be present and ready to step in whenever it’s necessary.